1 Kanal House Design
For the construction cost of 1 Kanal house, we will start from labour foundation till plaster and we will tell you about what things are included in the grey structure.
The most common question of the peoples when they call and ask about grey structure items and rate are as follow :-
- Approx now a days grey structure till plasters labor rate is 500/Sft
- Its depends on the design and location of the projects
- 1 Kanal house covered area of 2 storey house is approx starting from 5500-Sft
Labour costs for the 1 Kanal House = 2,750,000/- PKR (Approx Lump Sum)
Till Grey Structure work ( Including outside plaster work and no need to pay extra for the outside work )
Brick Blast (RORI) required for the PCC 1 Kanal House Construction
PCC Stand for Plain Concrete Cement. For the flooring and foundation, the PCC you will need more than 4000-Cft for the 1 Kanal House flooring & foundation and do compact in a good way with compactor. Each truck comes with more than 1000-Cft, so you will need 4 trucks max for the flooring and foundation.
Bricks required for 1 Kanal House Construction?
Note* its Depends not the accommodation and plot depth.
Approximately 140,000 bricks need to build a 1 Kanal House from the foundation till the completion of the grey structure. ( if plot depth is 3 feet below road level) although bricks sizes are different it does not make much difference in the quantity. All you have to check the quality of the bricks it should be 1st class brick.
Sand Trolleys required for 1 Kanal House Construction
Approx you will need 24 trolleys for the 1 Kanal House.
Gravel required for 1 Kanal House Construction
You will need 5000-Cft crush ( gravel stone 1/2 inch ) for the construction slabs ( lentil ) and PCC.
Cement bags required 1 Kanal Construction
You will need 1600 cement bags for all the work including wall mortar plaster PCC and all outside work.
Termite required for 1 Kanal House Construction
After the completion of digging next step is the Termite check. Before starting the construction anti termite checker is necessary. If doesn’t check this will cause a lot of damage to your house foundation.
Back filling required for 1 Kanal House Construction
Back filling is the process of filling in the excavated area around a foundation or structure. The back fill material can be anything from soil to gravel and is usually compacted to provide support and stability. Back fill can also be used to insulate foundations or improve drainage.
Safety Grills & Door Frames for 1 Kanal House Construction
Steel work will be required at various stages of the construction. For example, Chougat steel is used for making door frames.
Steel required for 1 Kanal House Construction
(Slabs 2 stories with 2nd floor 230-Sft, windows and door beam)
Approx you will need 9,500kg steel for the all work like slabs, lentil and other miscellaneous work.
Electrical Pipes underground only piping included in the grey structure
In the market, there are so many types of electrical pipes available but some of them are good like
1-Popular
2-Turk Plast
Approx electric pipes expense is 180k without labour only piping, wall boxes and fan boxes and other miscellaneous items popular brand.
Gas, Water and Sewerage Pipes
Same here there are so many brands in the in the pipes as well most of them are local but some of them are the best
1-Popular
2-DURA
3-Turk Plast
Mud Roof Tiles required for 1 Kanal House Construction
Popular with roofing professionals and homeowners alike, mud roof tiles maintain their high status in the industry for their practical and visual appeal. As a beautiful, long-lasting and versatile building material, mud roof tiles offer a wide range of advantages and benefits that mean it has been so widely used, not just now, but for much of history. Coming into general use around the 12th or 13th century but still used even before this time, clay tiles have proven for many years that they are a fundamental roofing choice and will continue to be utilized for yet more years to come.
Items | QTY | |
Labor for covered ares as per drawing (Approx) | 5500-sft | |
Brick Blast (RORI) | 4000-Cft | |
Bricks | 140,000 | |
Trolleys of Sand | 24 | |
Crush (Gravel) | 1800-Cft | |
Cement | 1,600 Bags | |
Termite | 2-Times | |
Back Filling | Lump sum | |
Safety Grill / Door Frame | As per drawing | |
Steel | 9500-Kg | |
Electric Pipes | Lump sum | |
Electrician Labor | Lump sum | |
Plumbing Pipes | Lump sum | |
Plumber Labor | Lump sum | |
Mud Roof Tiles | As per drawing |