10 Marla House Design
For the construction cost of 10 Marla house, we will start from labour foundation till plaster and we will tell you about what things are included in the grey structure.
The most common question of the peoples when they call and ask about grey structure items and rate are as follow :-
- Approx now a days grey structure till plasters labor rate is 500/Sft
- Its depends on the design and location of the projects
- 10 Marla house covered area of 2 stories house is approx starting from 3600-Sft
Labour costs for the 10 Marla house
3600 sqft will be covered area till Grey Structure work ( Including outside plaster work and no need to pay extra for the outside work )
Brick Blast (RORI) required for the P.C.C 10 Marla House Construction
P.C.C Stand for Plain Concrete Cement. For the flooring and foundation, the PCC you will need more than 2550-Cft for the 10 Marla house flooring & foundation and do compact in a good way with compactor. Each truck comes with more than 1000-Cft, so you will need 2 truck max for the flooring and foundation.
Bricks required for the 10 Marla House Construction
Approx 98,000 bricks required for the 10 Marla house construction, 2 story building with 2nd floor 170/Sft including parapet wall and boundary wall if your plot depth is 3 feet down maximum from the road level.
Sand Trolleys required for 10 Marla House Construction
Approx you will need 15 trolleys for the 10 Marla House.
Gravel required for 10 Marla House Construction
You will need 2800-Cft crush ( gravel stone 1/2 inch ) for the construction slabs ( lentil ) and PCC.
Cement bags required 10 Marla Construction
You will need 1080 cement bags for all the work including wall mortar plaster PCC and all outside work.
Termite required for 10 Marla House Construction
After the completion of digging next step is the Termite check. Before starting the construction anti termite checker is necessary. If doesn’t check this will cause a lot of damage to your house foundation.
Back filling required for 10 Marla House Construction
Back filling is the process of filling in the excavated area around a foundation or structure. The back-filling material can be anything from soil to gravel and is usually compacted to provide support and stability. Back-filling can also be used to insulate foundations or improve drainage.
Safety Grills & Door Frames for 10 Marla House Construction
Steelwork will be required at various stages of the construction. For example, Chougat steel is used for making door frames.
Steel required for 10 Marla House Construction
(Slabs 2 stories with 2nd floor 170-Sft, windows and door beam)
Approx you will need 5500-kg steel for the all work like slabs, lentil and other miscellaneous work.
Electrical Pipes underground only piping included in the grey structure
In the market, there are so many types of electrical pipes available but some of them are good like
1-Popular
2-Turk Plast
Approx electric pipes expense is 160k without labour only piping wall boxes and fan boxes and other miscellaneous items popular brand. Electrical labor going to close you lump sum amount 70k approx.
Gas, Water and Sewerage Pipes
Same here there are so many brands in the in the pipes as well most of them are local but some of them are the best
1-Popular
2-DURA
3-Turk Plast
Roof Mud Brick Tiles for 10 Marla House Construction
Popular with roofing professionals and homeowners alike, mud roof tiles maintain their high status in the industry for their practical and visual appeal. As a beautiful, long-lasting and versatile building material, mud roof tiles offer a wide range of advantages and benefits that mean it has been so widely used, not just now, but for much of history. Coming into general use around the 12th or 13th century but still used even before this time, clay tiles have proven for many years that they are a fundamental roofing choice and will continue to be utilized for yet more years to come.
Items | QTY |
Labor | 3600 sqft |
Brick Blast (RORI) | 2550-Cft |
Bricks | 98,000 |
Trolleys of Sand | 15 |
Crush (Gravel) | 2800-Cft |
Cement | 1080 Bags |
Termite | 2 Times |
Back Filling | Lump sum |
Safety Grill / Door Frame | As per drawing |
Steel | 5500-kg |
Electric Pipes | Lump sum |
Electric Labor | Lump sum |
Plumbing Pipes | Lump sum |
Plumbing Labor | Lump sum |
Roof Mud Brick Tiles | As per drawing |