5 Marla House Design
For the construction cost of 5 Marla house, we will start from labour foundation till plaster and we will tell you about what things are included in the grey structure.
The most common question of the peoples when they call and ask about grey structure items and rate are as follow :-
- Approx now a days grey structure till plasters labor rate is 500/Sft
- Its depends on the design and location of the projects
- 5 Marla house covered area of 2 storey house is approx starting from 1900-Sft
Labour costs for the 5 Marla house
500 x 1900 = 950,000/- PKR (Approx Lump Sum)
Till Grey Structure work ( Including outside plaster work and no need to pay extra for the outside work )
Brick Blast (RORI) required for the P.C.C 5 Marla House Construction
P.C.C Stand for Plain Concrete Cement. For the flooring and foundation, the PCC you will need more than 1100-Cft for the 5 Marla house flooring & foundation and do compact in a good way with compactor. Each truck comes with more than 500-Cft and each truck cost 40,000/- PKR, so you will need 2 truck max for the flooring and foundation.
Total cost 80,000/- PKR (Lump sum)
Bricks required for the 5 Marla House Construction
approx 60,000 bricks required for the 5 Marla house construction, 2 story building with 2nd floor 170/Sft including parapet wall and boundary wall if your plot depth is 3 feet down maximum from the road level.
Now a days bricks rate of 1st Class is 18-Pkr.
60000 x 18 = 1080,000/- PKR
Sand Trolleys required for 5 Marla House Construction
Approx you will need 9 trolleys for the 5 Marla House.
Each trolley gonna cost you around 18k it depends on the distance and city
18000 x 9 = 162,000/- PKR
Gravel required for 5 Marla House Construction
You will need 1800-Cft crush ( gravel stone 1/2 inch ) for the construction slabs ( lentil ) and PCC.
The gravel price of Sargodha Plant is 155 Cft
1800 x 155 = 279,000/- PKR
Cement bags required 5 Marla Construction
Now a days the cement bags price is nearly 1470 PKR and you will need 630 cement bags for all the work including wall mortar plaster PCC and all outside work.
1470 x 630 = 926,100/- PKR
Termite required for 5 Marla House Construction
After the completion of digging next step is the Termite check. Before starting the construction anti termite checker is necessary. If doesn’t check this will cause a lot of damage to your house foundation. The approximate cost of this for 5 Marla houses is 38,000 PKR (one time).
Total cost 38,000 x 2 = 76,000/- PKR
Back filling required for 5 Marla House Construction
Back filling is the process of filling in the excavated area around a foundation or structure. The back-filling material can be anything from soil to gravel and is usually compacted to provide support and stability. Back-filling can also be used to insulate foundations or improve drainage.
Total cost = 200,000/- PKR (Lump sum)
Safety Grills & Door Frames for 5 Marla House Construction
Steelwork will be required at various stages of the construction. For example, Chougat steel is used for making door frames.
Total cost for Safety Grills and Door Frames is 300,000/- PKR (Lump Sum)
Steel required for 5 Marla House Construction
(Slabs 2 stories with 2nd floor 170/Sft, windows and door beam)
Approx you will need 2400/kg steel for the all work like slabs, lentil and other miscellaneous work.
The rate of Garde 60 is 269.
2600 x 269 = (699400) Approx 700,000/- PKR
Electrical Pipes underground only piping included in the grey structure
In the market, there are so many types of electrical pipes available but some of them are good like
1-Popular
2-Turk Plast
Approx electric pipes expense is 80k without labour only piping boxes and fan boxes and other miscellaneous items popular brand. Electrical labor going to close you lump sum amount 60k approx
Electrical pipes 80,000/- PKR
Electrician labor 60,000/- PKR
Gas, Water and Sewerage Pipes
Same here there are so many brands in the in the pipes as well most of them are local but some of them are the best
1-Popular
2-DURA
3-Turk Plast
Approx plumber and PPRC pipes going to cost you for the 5 Marla House 270,000/- PKR
And labour for the all work till grey structure 80,000/- PKR
Roof Mud Brick Tiles for 5 Marla House Construction
Popular with roofing professionals and homeowners alike, mud roof tiles maintain their high status in the industry for their practical and visual appeal. As a beautiful, long-lasting and versatile building material, mud roof tiles offer a wide range of advantages and benefits that mean it has been so widely used, not just now, but for much of history. Coming into general use around the 12th or 13th century but still used even before this time, clay tiles have proven for many years that they are a fundamental roofing choice and will continue to be utilized for yet more years to come.
The total cost is 110000/- PKR.
Items | Pr/sqft Price | QTY | Amount | Total |
Labor | 500 | 1900 | 950,000 | 5,353,000(PKR) |
Brick Blast (RORI) (Lump sum) | 80,000 | |||
Bricks | 18 | 60000 | 1,080,000 | |
Sand | 18000 | 9 | 162,000 | |
Crush (Gravel) | 155 | 1800 | 279,000 | |
Cement | 1470 | 630 | 926,000 | |
Termite (2-Times) | 76000 | |||
Back Filling (Lump sum) | 200,000 | |||
Safety Grill / Door Frame (Lump Sum) | 300,000 | |||
Steel | 269 | 2600 | 700,000 | |
Electric Pipes | 80,000 | |||
Electric Labor | 60,000 | |||
Plumbing Pipes | 270,000 | |||
Plumbing Labor | 80,000 | |||
Roof Mud Brick Tiles | 110,000 |